What is happening in Farmington?

These two videos clearly tell the story and show what the Coalition is up against.

Please watch in succession. They are full of information and provide a clear timeline and picture of the issues involved.

On May 1 of 2024, a few Farmington residents received notice of a May 14th Public Hearing and Planning Commission vote to rezone land that sits next to their homes. The intended land was Fountain Valley Golf Course and land just south of the golf course owned by ISD 192, a combined 348 acres.

Both parcels had been annexed to Farmington by Castle Rock Township. In the Orderly Annexation Agreement, the city of Farmington agreed that any industrial or commercial use of the property would require consent from the Township.

The residents were not aware that Tract Management, a data center developer from Colorado, had been working with the city for months to put the plans in place for the purchase of the land parcels, the rezoning of the property, along with the details of the project. This would be the largest hyperscale data center built in Minnesota to date. The project would consist of 12 buildings, up to 80 feet tall, 708 MW, 2.53 million square feet, an electrical substation, and several hundred generators with over a million gallons of stored fuel.

Throughout the summer of 2024, the city of Farmington went forward, working with Tract Management on the AUAR, PUD and plat, and approving all of the decisions necessary for the project, including the plan to amend the Comprehensive Plan to accommodate this new zoning.

The City of Farmington’s agreement with Castle Rock Township within the Orderly Annexation Agreement was ignored.

The Coalition representatives filed legal action against the city in November of 2024.

On January 14, 2025, the Castle Rock Township board voted unanimously to file legal action against the city of Farmington for breach of the Orderly Annexation Agreement. Their legal filing is pending.

On January 16, 2025, Sen Bill Lieske and Rep Drew Roach released their draft of a bill to be presented the following week to the Minnesota State Senate, designed to regulate the zoning of hyperscale data centers., You can see the Senate Bill HERE.

News and Media Related to the Data Center and Citizen’s Opposition

The following are links to the ongoing news pieces and articles written about this issue and citizen’s efforts.

NEWS VIDEOS

KSTP 5 Eyewitness News, Renée Cooper - Jan 14, 2025

Castle Rock Township Vote

ABC 6 News KAALTV-Sept 17, 2024

Debate grows regarding proposed Farmington data center

KSTP 5 Eyewitness News, Renée Cooper - Sept 16, 2024

Farmington golf course redevelopment moves forward as neighbors voice opposition

FOX 9 Minneapolis, Babs Santos -St. Paul. May 7, 2024

Farmington data center on golf course site has neighbors ready to fight

ARTICLES

Sun ThisWeek, Kara Hildreth - Mar 20, 2025

Coalition files ethics complaint against city about data center

Star Tribune, Eva Herscowitz - Mar 3, 2025

Emails show Farmington tried to 'offset the opposition' to data center

Pioneer Press, Mars King - Jan 25, 2025 (article via Yahoo! news

Minnesota lawmaker introduces bill that could restrict new data center construction

Pioneer Press, Mars King - Jan 22, 2025

Minnesota Lawmaker Introduces Data Center Zoning Bill

Sun Thisweek, Kara Hildreth - Jan 22. 2025

Castle Rock files lawsuit against Farmington over data center

Bring Me the News, Tommy Wiita - Jan 9, 2025

Farmington residents file lawsuit against city to prevent $5B data center plan

Star Tribune, Eva Herscowitz - Jan 8, 2025 (link via MSN)

Farmington residents couldn’t get answers about a proposed data center. Then they saw the NDA.

Pioneer Press, Mars King- Jan 8, 2025 (link via MSN)

‘We were completely ignored’: Farmington residents sue the city in attempt to stop $5B data center park

Data Center Wires-Dec 20, 2024

Farmington, MN Faces Lawsuit Over Tract Data Center: Community Groups Claim Environmental and Resource Strain

Public Record Media by Mike Kaszuba - Dec 19, 2024

In Farmington, a homeowner battle a data center and lack of information

Data Center Dynamics, Niva Yadav - Dec 19, 2024

Minnesota's City of Farmington sued over Tract data center build

Public Records Media, Mike Kaszuba - Dec 19, 2024

In Farmington, a homeowner battles a data center and lack of information

KSTP, Krystal Frasier - Dec 17, 2024

Farmington sued by group over plans to build data center

MPR New, Kirsti Marohn- Dec 16, 2024

Farmington residents sue city over proposed data center

The Minneapolis Star Tribune, Eva Herscowitz, -Dec 13, 2024 (link via MSN)

Farmington residents sue city over proposed data center campus

MPR News, Kirsti Marohn - Dec 11, 2024

Data centers spark opposition from residents, concerns over energy use

Sun Thisweek, Kara Hildreth -Dec 5, 2024

Farmington council approves data center despite community opposition

Pioneer Press, Mars King - Dec 1, 2024 (link via MSN)

$5B data center park in Farmington moves forward despite objections from some residents

Sun Thisweek, Kara Hildreth - Nov 29, 2024

Farmington Planning Commission approves data center final plat | Farmington | hometownsource.com

Sun Thisweek, Kara Hildreth - Nov 13, 2024

Farmington Planning Commission approves data center final plat

Star Tribune, Eva Herscowitz - Nov 1, 2024

Proposed data center in Farmington sparks resident pushback

Citizen Portal -Oct 22, 2024

Residents rally against controversial rezoning plan in Farmington

Limitless Media, Will Wight - Oct 21, 2024

Local Citizen Group to Hold Public Meeting on Planned Hyperscale Data Center in Farmington, Minnesota

Pioneer Press, Mars King -Oct 6, 2024

Some residents want to keep the ‘farm’ in Farmington as developer pitches data center park

Sun Thisweek, Kara Hildreth - Sept 17, 2024

Farmington Planning Commission approves land rezoning for data center

KSTP by Renée Cooper - Sept 17, 2024

Costco-sized” buildings concern Farmington neighbors as development moves forward

Sun Thisweek, Kara Hildreth, - Sept 12, 2024

Farmington homeowner challenges technology park, data center

Data Center Dynamics, Dan Swinhoe - Sept 11, 2024

Tract plans 343-acre data center park outside Minneapolis, Minnesota

Data Center Dynamics, Dan Swinhoe - Sept 10, 2024

Building for the long-term: Grant van Rooyen’s Tract masterplan

Minneapolis/St. Paul Business Journal, Mark Reilly - Sept 10, 2024

Data center developer Tract eyes Farmington golf course

Finance & Commerce, Brian Johnson - Sept 9, 2024

Denver developer proposes major data center project in Farmington

Data Center Dynamics, Niva Yadav - May 8, 024

Minnesota golf course outside Minneapolis set to become data center

Fox 9, Babs Santos - May 7, 2024

Proposed Farmington data center has current residents on edge

Republican Eagle, Kara Hildreth - Aug 4, 2017

Farmington ripe for landing data center